More than a decade in the making, the Guam Memorial Hospital Authority's Maternal and Child Health renovation and expansion project broke ground Wednesday, bringing the government a step closer to fulfilling a commitment made in 2014.
Dr. Joleen Aguon, GMHA's interim hospital administrator and CEO, called the groundbreaking a "blessing" as the hospital marked the milestone the day before Thanksgiving. She also recognized that for "many families on Guam, life began here at Guam Memorial Hospital."
"This is where mothers bring their babies into the world. This is where our most fragile infants fight the first battles in our NICU (Neonatal Intensive Care Unit) and this is where families have the most happiest moments and sometimes the hardest moments in their lives," Aguon said.
The project will provide Guam with a new family birth center where mothers will be able to labor, deliver and recover in one room with their families beside them.
Currently, mothers may be moved as many as four times during labor and delivery, according to Dr. Thomas Shieh, a local obstetrician and gynecologist who has practiced on Guam for 30 years.
Shieh was among the physicians recognized by GMHA during the ceremony for their contributions to advancing the project over the years.
"Nearly a decade of advocacy has brought us to this moment, but the work is not done. For years, I worked to bring nurses, pediatricians, neonatologists, OB/GYNs, mothers, and families to the table to help shape a maternity and nursery facility worthy of our community," he said.
The project follows years of concerns over the hospital's aging infrastructure, including mold growth, signs of water leaks and air conditioning problems, including in the obstetrics ward.
"I brought then-Governor Eddie Calvo to GMH to witness firsthand during his final year in office, he saw the conditions confronting our mothers and babies," Shieh said.
That effort resulted in $1 million being authorized for the project's design. However, Shieh said the design was "shelved for eight years."
"Today, I sincerely congratulate Dr. Ricardo Eusebio and Dr. Aguon for listening and helping move this long-awaited project forward," he said.
The project's specifications state that the renovation aims to bring the hospital's obstetrics ward, which includes Labor and Delivery, Maternity, Postpartum, Nursery and the Neonatal Intensive Care Unit, up to the 2010 Facility Guidelines Institute standards for hospitals and outpatient facilities.
During the ceremony, Aguon acknowledged the inadequate spaces in which physicians and hospital staff have worked for years.
"Many of you helped shape these plans years ago, and you also never gave up on them. You have given excellent care in spaces that were not built for what you do. This new unit is for all of you and for every family that you care for," Aguon said.
The project was awarded to Northern Construction and will be completed in four phases.
Phase I will focus on the Labor and Delivery area, including the cesarean section room, Labor, Delivery and Recovery (LDR), Labor, Delivery, Recovery and Postpartum (LDRP) rooms, and supporting areas.
According to the project specifications, work is scheduled to begin within 30 days of the Notice to Proceed and must be substantially completed and ready for occupancy according to a schedule negotiated with GMHA. Areas designated for Phase IV will be excluded from this phase.
Phase II will focus on the Postpartum area, including all postpartum and supporting spaces. Work will begin according to a schedule established with GMHA and must be completed and ready for occupancy as negotiated with the hospital.
Phase III will involve the NICU area, including the hospital lobby, existing courtyard infill, a new stairwell and elevator, first-floor improvements, and second-floor NICU and postpartum areas not included in Phase II.
The specifications require the Guam Fire Department to inspect and approve all emergency exit modifications before existing stairways can be removed. Work will begin according to the schedule established with GMHA and must be substantially completed and ready for occupancy as negotiated with the hospital.
Phase IV will begin after Phase III is completed and will focus on the existing NICU area, along with the remaining Labor and Delivery and Postpartum areas.
Hospital operations are expected to continue throughout construction. The project specifications indicate that temporary facilities may be necessary during the first and second phases.
"We will build in stages and the care you count on will continue. A hospital is not measured only by its buildings. It's measured by how people are cared for when they walk through our doors. This new space will help our teams do what they already do so well, with the room and tools they deserve to have," Aguon said.
A total of $18 million has been invested in the project. While construction moves forward at GMHA, Gov. Lou Leon Guerrero emphasized that work must also continue toward building a new hospital.
"This is a great demonstration of what the work we have done. It is also the beginning of many work that we should do to build a new hospital," Leon Guerrero said.
"Some people say we don't need a new hospital right now because we have to fix our systems and our processes. Let me be very clear. That is being fixed today as we speak. You cannot exclude one without the other," she added.
During the ceremony, Leon Guerrero also announced that the architectural and design contract for the new hospital has been signed.
"And all of you here will be sitting with the architects to design the hospital the way it should be designed to work your processes, your workflow, and all your systems so that it can work for you, for you, so you can deliver that patient quality to our people," Leon Guerrero said.
The cost of the architectural and design contract is $90.8M.